Project Type
Upgrade of SAP S/4 HANA 1809 to S/4 HANA 2022.
Migration of S/4 HANA from on premise to AWS Cloud.
Team Size
6
SAP Environment
SAP S/4 HANA
Duration
Dec 2022 to till date.
Responsibilities:
- Prepared the project plan with detailed activities for the upgrade of S/4 HANA 1809 to 2022.
- Implemented all prerequisites SAP notes for SI checks, ATC, and readiness check report.
- Ran the relevant report and generated the readiness report in SAP portal.
- Ran the ATC check for custom code adaptation and SI checks report for Simplification items checks.
- Upgraded to S/4 HANA 2022.
- Migration of the 3 TB S/4 HANA 2022 system using HANA HSR methodology from on premise to AWS Cloud.
Project Type
Uninstallation of add-on and Upgrade of SAP systems.
Team Size
4
SAP Environment
SAP ECC, BW, GRC, GTS, CRM
Duration
April 2022 to Dec 2022
Responsibilities:
- Uninstallation of addons.GTS was carved out from ABAP stack where both GTS and GRC was implemented together.
- Prepared the overall project plan for migration and upgrade including detailed cutover activities.
- As a team lead, coordinated the upgrades of all the SAP systems BW, CRM ABAP, CRM JAVA, Solution manager, ECC, GTS, GRC…..
- Migration of SAP system from on premise to AWS Cloud. Used SAP parallel export/import for the migration.
- Upgrade of GRC & GTS SAP systems to latest Support pack.
Project Type
Migration from On-premises to AWS Cloud
Team Size
8
SAP Environment
SAP ECC, BW, Solution Manager, and portal.
Duration
May 2020 to April 2022
Responsibilities:
- Migration of existing SAP systems from on premise to AWS Cloud.
- Integration with Open text post migration to AWS cloud.
- Worked with Database team to enable TDE encryption and ASM configuration.
- Enabled SSL for portal and backend ECC.
- Prepared and shared OSM to BAU team.
- Prepared and shared the daily health check which must be executed daily and report to be send to client.
SAP Basis
Project Type
Basis Run support (Oct 2019 – Apr 2020)
Team Size
17
Role
Basis TPM
SAP Environment
S4Hana, TPM, HANA 2.0 and BO Data services, BW on HANA systems, Solman, GRC, PO & Fiori.
Responsibilities:
- Support of S4Hana, Fiori, BW4HANA, BODS, GRC and TPM systems. All SAP systems are running on HANA 2.0.
- All SAP systems are HA with pacemaker. Both SCS/ERS and Database are managed thru pacemaker.
- Prepare monthly maintenance plan for OS patching with zero downtime. Prepare other maintenance plan for maintenance activities.
- Present weekly performance review for S4, TPM and PO systems
- Fortnightly review of EWA analysis and implementation plan.
- Drive Governance call on a weekly basis with customer.
- Was part of successful Wave2 and Wave 3 Golive.
- Prepared and shard SOP for different technical document.
- Prepared monthly Shift roster and align resources for monthly maintenance activities.
- Brought shift handover and shift lead concept which helped the team manage their deliverables effectively and had filled the gaps.